This complex project to re-install a plant that had been moved from RSA (and left in storage for a number of years), was awarded to Hogarths by the client knowing the strength of the Hogarths site teams.
The site work was supported by Viva Engineering in the complex integration of new steelwork and equipment into the existing structures.
The new steelwork was Hot Dipped Galvanized and shipped to the site once Bureau Veritas inspected and released loads for cross-border transport.